OPC communications cost effectively links paper machine's dye skid and color control, Solutions!, Online Exclusives, September 2002

OPC COMMUNICATIONS COST EFFECTIVELY LINKS PAPER MACHINE’S DYE SKID AND COLOR
CONTROL
Normand
Raymond, Instrumentation Supervisor,
Technical and Office Products Division,
FiberMark, 16, Brattleboro, Vermont, USA
Phone: 802-257-5996
Email: nraymond@fibermark.com
The
world’s leading manufacturer of paperboard for office products upgraded
a paper machine to improve color quality and help reduce machine downtime
to only 35 minutes when changing colors and grades. It achieved these
goals by adding an automated liquid-dye skid linked to a color control
system via OPC (Microsoft Object Linking and Embedding [OLE, now Active
X] for Process Control.)
FiberMark,
Brattleboro, Vermont, USA makes some 200 different colors and grades of
paperboard products on a dedicated, multi-layer paper machine. Converter
customers turn these products into the report covers, pendant files, 3-ring
binders, etc., familiar to every office. Because many customers have switched
to just-in-time inventories, FiberMark has had to increasingly accommodate
shorter runs of smaller quantities with faster turnaround times. This
has resulted in color/grade changeovers rising to as many as two or three
a day. The company urgently needed to establish color quickly, and then
stay on color.

Photo 1. Portion of the Emerson DeltaV™ controller running
the new dye skid at FiberMark, Brattleboro, Vt. Shown (left to right)
are the controller’s backplane-mounted power supply card, CPU card, and
four FOUNDATION™ fieldbus communications cards having two fieldbus
segments each. Fieldbus instruments provide almost all analog functionality.
The integrated DeltaV digital automation system is a key component of
Emerson’s PlantWeb® digital plant architecture.
Each changeover
took up to two hours and produced excessive scrap when lining out color
during restart. The machine has seven head boxes for producing up to a
seven-layer web comprised of precisely colored liners on the outside and
filler layers between. The liners are generally dyed white pulp, while
filler layers are a combination of recycle and pulp that may or may not
be dyed. An older Measurex 2002 gauging system monitored basis weight,
moisture content, and single-side color. Adjustment of these variables
was manual, as was the addition of powder and liquid colorants.
Automation
the Answer
To improve operations, FiberMark recently invested in:
- Automated color
control to gauge color accuracy and density, calculate the paper machine’s
speed, stock consistency, and paper dry weight, and then determine the
proper dye amounts to create and maintain the correct color, and
- An automated liquid-dye
mixing and distribution skid to replace the manual weighing, hand mixing,
and manual dumping of dye into pulpers. The skid receives instructions
from the color system to meter, mix, and deliver the correct volume
of the dye blend.
Color
sensing has been removed from the older Measurex equipment (basis weight
and moisture content remain) and placed in a new Honeywell-Measurex MX
Open monitoring/control system having two-sided color gauging. The gauge
on one side serves as the master or reference for color accuracy and density;
the gauge on the other side as a slave to match the reference. Although
MX Open is not the latest technology, it’s adequate to the FiberMark task
and substantially less expensive than newer, more sophisticated color
control.
The 24-head skid (4 banks of 6 heads), built by Bran+Lubbe, covers the
full color wheel and is automated by Emerson Process Management’s PlantWeb®
digital plant architecture, whose key component is an integrated DeltaV™
digital automation system. FiberMark initially considered adding the skid
to an existing Emerson RS3 distributed control system (DCS) running the
paper machine’s wet end, but opted for standalone control using the more
advanced digital plant architecture approach because of its newer and
open technology, smaller footprint, lower cost, ease of use, handy tools
and diagnostics, and scalability for possible future expansion into a
mill-wide control system. The mixed dye is delivered at the correct flow
rate to the paper machine at four locations: drain, stuff box, suction
side of the fan pumps, and top side/bottom side.

Photo 2. DeltaV PC operator workstation mounted on the dye skid.
The workstation connects to the controller via an open Ethernet control
LAN.
During
evaluations leading to the skid’s control system specification, PlantWeb
automation architecture proved the best for the packaged equipment. The
DeltaV system’s field-mountable controllers have a form factor resembling
PLCs which in the past have been chosen to run skids of all types. The
technology additionally relies on open PC workstations, an open Ethernet
local area network (LAN) tying controllers and workstations together,
and open buses—such as FOUNDATION™ fieldbus -- for instrumentation.
What’s more, the architecture’s database is global, object oriented, and
requires no controller-to-workstation database mapping. Control development
is accomplished through drag-and-drop graphic configuration using pre-engineered
control modules.
The architecture
helpfully offers a full discrete point capability -- either by bus communications
or hardwired I/O cards -- to handle the many switched devices present
on a color skid. FiberMark would have liked to have specified Actuator/Sensor-interface,
an open bit-level bus (AS-i) for discretes, but an AS-i communications
card, since released, was still in beta testing.


Photos 3 and 4. Normand Raymond, FiberMark Instrumentation
Supervisor, checks two DeltaV discrete I/O cards mounted in a cabinet
distant from the controller and served by a fieldbus segment running nearby.
Although fieldbus is primarily intended for analog devices, DeltaV discrete
I/O cards can directly reside on the bus. In FiberMark’s case, the fieldbus-remoted
I/O cards avoid the need to run a second set of wires and conduit all
the way back to the controller.
FiberMark performed
configuration of the skid’s controls, graphics, and communications with
the assistance of the skid maker and the control system’s local representative.
Logic was written in the IEC 61131.3 Function Block Diagram and Sequential
Function Chart languages. Most of the skid’s analog instruments reside
on fieldbus segments wired back to cards on the skid’s single controller.
Fieldbus saved much wiring and has made for superior troubleshooting,
maintenance, calibration, and alarming.
A few 4-20 mA devices not available in fieldbus were wired to I/O cards
on the controller backplane, as were all but two discrete points. Those
points, distant from the controller, were picked up by a remoted DeltaV
discrete I/O cards directly residing on a nearby fieldbus segment, an
arrangement that avoided the need to run a second set of wires and conduit
all the way back to the controller. Although fieldbus is primarily used
with analog devices, the DeltaV system allows its discrete I/O cards tap
into the bus.
How to Integrate
the Incompatible Controls?
After the skid automation was chosen, FiberMark was faced with integrating
it with the color control. This was no small task because the two systems
are not natively interoperable and any link between them would need to
carry approximately 250 points of realtime, bi-directional, peer-to-peer
data. Further, data exchange between the skid controller and the color
control’s Application Manager varies greatly in volume -- little during
steady-state papermaking conditions, very high during startup after a
color/grade change. Data includes dye choices, pump setpoints and speeds,
routing valve positions, flow meters, etc.

Photo 5. FiberMark is the world’s leading manufacturer of paperboard
used for such familiar office products as report covers, 3-ring binders,
day planners, pendant files, etc.
Three communications
methods for linking the two systems were looked at: point-to-point hardwiring,
an RS-485 serial link, and OPC. Hardwiring was immediately seen as costly
and impractical. A 1 Mbps RS-485 connection using the open Modbus communications
stack could possibly do the job but might not be fast enough and would
require the preparation of custom drivers at both ends. OPC was the best
answer because it would allow the incompatible equipment to communicate
via faster Ethernet without FiberMark having to prepare or maintain drivers.
With OPC, equipment manufacturers prepare proprietary protocol-to-OPC
Ethernet drivers for each of their devices. The end user can then transparently
plug the devices into his Ethernet network. Both the DeltaV system and
MX Open accommodate OPC and Ethernet on any PC running Windows NT.
The OPC link was developed by FiberMark using both the skid’s redundant
10/100 Mbps Ethernet control network and the color system’s non-redundant
10 Mbps Ethernet network. (See simplified block diagram.) Emerson designed
the DeltaV system for OPC right from its inception; as a result, configuration
and operation were smooth and seamless. We stumbled a bit at the color
control end because the point capacity of its OPC connections was initially
confusing. We eventually established 18 connections in each direction
categorized by function -- setpoints, remote setpoints, mode, auto, cascade,
manual, etc. If we need to add a point or make a change, we know exactly
where to go in the logic.
Everything
in One Computer
Unlike most OPC applications, where an OPC server serves several OPC clients,
the FiberMark application interconnects two OPC servers. Server-to-server
communications require an OPC software bridge, in this case the Emerson
DeltaV OPC Mirror™. Because of the skid automation’s highly developed
OPC capability, all OPC functions could be loaded into a DeltaV Application
Workstation. Included in this workstation are:
- DeltaV OPC server
software,
- MX Open ODX-protocol
OPC server software, and
- DeltaV OPC Mirror
software.
Not only were hardware
costs cut, but also the fastest translations were assured by confining
all OPC work in one PC and fitting that 800 MHz Pentium III machine with
512 Mbytes of RAM. The mirror was configured in an Excel spreadsheet,
which allowed the 250 points to be quickly listed through copy-and-paste
methods.
In a another move
to cut costs, floor cabinet space, and system complexity, every operator
and engineering workstation assigned to the skid system carries a third
Ethernet network interface card (NIC) to allow it to connect to the color
control system’s LAN and display the color space window. One skid workstation,
at the dry end of the machine, is some 330 feet from the color control
LAN. To add a colorspace window to that station, an Ethernet fiber optic
spoke was run. All other LAN cables, and the fieldbus cables, are copper.
A
Little Customization Added
Rounding out the new skid and color control systems are two additional
pieces of software prepared by FiberMark and inserted into the skid system’s
program. One is a simple block in the controller that produces a one-second
clock signal—a heartbeat—sent via OPC to the color system and
returned. Should the OPC tie fail, the heartbeat will stop and the two
systems will alarm and continue to control as last instructed. A heartbeat
is necessary because the application used OPC report by exception.").
If the link failed without the heartbeat, no values would change and operators
wouldn’t know that a communications failure had occurred.

Diagram 1. Simplified block diagram of the skid automation system
and its OPC tie to the color control system.
The
second piece of software is a visual basic program, featuring an OPC driver,
loaded into a dedicated PC. It captures and stores all data traversing
the two automation systems. The program allows FiberMark to analyze problems
by using sorting software to backtrack through the database. The volume
of data points is significant; more than 30,000 were collected over a
recent two-day period.
Outstanding
Results
The OPC interconnect between the dye skid and the color control is working
very well. The only weak point seems to be a bottleneck that occurs occasionally
during times of very high data exchange, caused by the color system’s
LAN being limited to 10 Mbps. Primarily affected are this system’s HMIs,
which occasionally lose updates for a few seconds because of their lower
priority status. To assure that a short loss of visibility causes no production
problems, color control is temporarily suspended as last instructed. The
higher priority OPC data exchanges with the skid don’t appear to be affected.
Paper machine grade/color changeover time has been drastically reduced.
The average today is just 35 minutes, compared to up to 2 hours previously.
Color accuracy -- on both sides of the sheet -- has been much improved,
and scrap is substantially reduced as well. All of these benefits have
been largely generated by the new dye skid and color control. A second,
less complicated PlantWeb project that improved filler layer control provided
the remainder of the gain.